UK Parliament’s Public Accounts Committee (PAC) has published a report calling for stronger protections for taxpayers and consumers, who will provide most of Sizewell C’s financing and bear most of its risks. The government has relinquished majority control to a delivery body primarily owned by private investors. The nuclear power project is expected to cost between GBP 40.5 billion and GBP 47.7 billion, with construction due to finish between 2039 and 2043.
The reactor design has a record of substantial delays and cost increases internationally, and no comparable nuclear power station has been completed on time and within budget. If costs exceed projections, private investors would have to provide only an additional GBP 30 million, compared with an additional GBP 9.8 billion paid by consumers during construction and GBP 12 billion through higher energy bills over the 60 years of the operating contract. This allocation raises concerns about whether investors have sufficient incentives to control costs, while the government’s ability to intervene directly is likely to be constrained. Taxpayers would also cover any decommissioning costs exceeding the funds set aside by Sizewell C Ltd.
The government should explain how it will protect consumers and taxpayers and assess whether those protections work. Project reports should be published every six months rather than annually, including expected effects on consumer bills and forecast investor returns. The PAC also calls for Funded Decommissioning Programme reports every five years, showing how available funds compare with expected costs. To secure the projected domestic economic benefits, the government should set out how it will ensure that 70% of construction spending takes place in the UK and that associated jobs remain in the country.